Nylect story begins in 1976 as a humble general sub-contractor in a small local workshop. The company then was registered as Nylect Industrial Services with the office at Dover Avenue. This humble beginning gave birth to Nylect’s story of success. Now, Nylect with more 100 staff strength is a regional player to a number of well-known MNCs, with head office in Singapore and overseas operations Vietnam, Indonesia, Malaysia and China.​

The Major Events

1982

 

The company Nylect Engineering Pte Ltd was incorporated in Singapore.  Registered address Blk 4004 Depot Lane, #01-07, Singapore 109758, with a issued paid-up capital of S$ 200K.

The 1st job commenced was Electrical installation and Fire alarm System for concrete factory Phase II, and later Orchard Hotel Meriden for an electrical installation including sound, CATV and TAS system c/w additional works

1983

 

Public Works Department
Commenced Electrical installation including communication and telephone system for level 2 of Kent Ridge Hospital

1984

 

CTS Singapore Pte Ltd

Commenced Electrical design, supply, installation, commission and lighting protection system to existing factory at Ang Mo Kio Industrial Park II c/w additional works​

1985

 

Telecommunication Authority of Singapore
Commenced Electrical installation works to telephone exchanges

1986

 

The Company was CIDB registered under G3 - Electrical Work

MiniScribe Peripherals Pte Ltd
Commenced Electrical installation to 2nd & 3rd storey at Blk 4012 and fire protection system at Blk 4010, 6th & 7th storey at Ang Mo Kio Industrial Park 1

1987

 

Maxtor Singapore Ltd
Commenced HT and LT Electrical installation to 3rd storey light industrial factory at Ang Mo Kio Ave 9

Seagate Technology International

Commenced upgrading HT/LT at Blk 16 c/w main switchboard at cleanroom and production test area at Seagate Kallang​

1989

 

SGS-Thomson Microelectronics (Ang Mo Kio)
Commenced design, supply and installation of HT/LT to 9 storey block with basement at Ang Mo Kio Industrial Park II

1990

 

Pepperl & Fuchs (S) Pte Ltd
Commenced design, submission, supply, installation, testing and commission of HT and LT works to 4 storey light industrial factory building at Ayer Rajah Crescent

1991

 

Singapore Telecom
Commenced Brunei - Singapore submarine cable P/J Singapore civil work



The Mandarin Singapore
Commenced Turn-Key M&E services to renovate the Mandarin Singapore top of ‘M’



Singapore Broadcasting Corporation
Commenced upgrading of LT main switchboard at Caldecott Hill Andrew Road, SBC

1992

 

The Company was CIDB upgraded under: G4 - Electrical Work

1993

 

The Company was CIDB further upgraded to : ME05 - L4 Electrical Work

AT&T Microelectronics Pte Ltd


Commenced Turn-key, design, supply, installation, testing and commissioning of air-conditioning system, electrical system, utilities, building and partition works to outfit a factory at No. 3 Kallang Sector

1994

 

The Company was further upgraded to : ME05 - L5 Electrical Work

Chartered Semiconductor Manufacturing Pte Ltd
Commenced supply and install complete electrical system for proposed CSM FAB II factory at Woodlands Industrial Park D

1995

 

The Company paid up capital was increased to S$ 1 million



Apollo Enterprise Ltd
Commenced supply, delivery, installation, testing & commissioning of the HT electrical system for proposed new substation / M&E plant room to existing Apollo Hotel

Jurong Point Realty (P) Ltd - Jurong Point
Commenced design and build on electrical system, security, CCTV, CATV and fire intercom systems for proposed commercial development at Jurong West Central 2/Upper Jurong Road

1996

 

Singapore Post Pte Ltd
Commenced electrical installation for proposed 3-storey postal delivery base at Kian Teck Way

Changi International Logistics Centre
Commenced electrical installation for proposed extension Warehouse Complex at 19 Loyang Way

1997

 

The Company moved to present premises at Nylect Industrial Building No. 1 Woodlands Sector 1, Singapore 738309

1999

 

SSMC Hook Up
Commenced Cleanroom Machine Hookup for new SSMC plant

2000

 

Nylect Technology Limited was incorporated and listed on the Singapore Stock Exchange.

2002

 

Obtained certification of our Integrated Management System from PSB covering ISO 9000:2000, ISO 14001:1996 and OHSAS 18001:1999

2003

 

Reorganized Field Operations Departments into Teams to better serve our customer

2004

 

Infineon HQ.
Commenced design, supply and installation of electrical system

SIA Engineering Co Ltd
Commenced electrical installation for Hangars 4 & 5

2006

 

Deutsche Bank
Commenced supply and installation testing, commissioning and maintenance of the advance M&E services at One Raffles Quay

2008

 

Nylect International Pte Ltd acquired Nylect Engineering Pte Ltd and took it private.

Starhub Green
Commenced electrical installation to 7 storey hi-tech multiple user industrial development with a basement at Ubi Ave 1

2009

 

Singapore Aerospace Engine.
Commenced electrical installation to 2 storey engine overhaul building at Loyang Way for M/S SAESL

313 Shopping Center
Commenced installation of switchgears, transformers, diesel generator sets, HT/LT retriculation works in a new erection of a 7 storey commercial building with 3 basements at Orchard Road Somerset Road

2010

 

Rolls Royce Achord
Design and build of industrial development comprising of a single storey manufacturing building with 2 storey ancillary facilities & utilities support areas at Seletar Aerospace Park Singapore.

2012

 

IM Flash
IMFS FAB 10 – Hook up HK26 Electrical System

Jurong Gateway
Commenced electrical installation and security system of a 17 storey building at Jurong Gateway Road Boonlay Way



Obtained certification of our Integrated Management System from Certification International covering ISO 9001:2008, ISO 14001:2004 and OHSAS 18001:2007.


 

2013

 

Stamford American International School Phase 2

Commenced electrical and structure cabling works package at Upper Serangoon.

 

Schenker Singapore Pte Ltd

Design and build of a Part 3 / Part 6 Storey single user warehouse with Ancillary Office Development Business 2 for Schenker Singapore Pte Ltd

 

Successful Surveillance Audit and Recommended for continued registration for ISO 9001, ISO 14001, ISO 18001.

2014

 

Seagate

Design and build 6 storey, Part 9 storey single user Business Park Development with Ancillary facilities and 3 basement carpark floors at Ayer Rajah Avenue.

 

Gems World Academy

Proposed International School at Yishun Ave 6 / Ave 1.

 

Achieved bizSAFE Level STAR in Work Safety and Health Council.

 

JTC Corporation

Proposed Erection of a Single-User Industrial Development (Business 2) Consisting of 1 Block of 3-Storey / Part 2-Storey, 1 Block of 3-Storey and 1 Block of 8-Storey Buildings at Tukang Innovation Drive

 

LF @ Bulim

Design, supply and Installation of Electrical Services and their Associated works for the Proposed Erection of a 9-Storey Single User Ramp up Warehouse with the Mezzanine Office and Temporary Staff Canteen at Jurong West Street 22/23

 

Successful Surveillance Audit and Recommended for continued registration for ISO 9001, ISO 14001, ISO 18001.

2015

 

Kingsland Data Centre

Design and Build Project (TOP) for Data Centre at Sunview Way.

 

Kuhne + Nagel (K + N) Real Estate Pte Ltd

Erection of a 7-STorey Single User Warehouse with Ancillary Office Development at Pioneer Cresent.

 

Airbus @ Seletar

2 - Storey Single User Industrial Development at Seletar Aerospace Crescent

 

GSK HQ

Electrical Installation to Proposed GSK Asia Headquarters at One North

 

Successful Re-Certification Audit and Re-Certified for ISO 9001, ISO 14001 and ISO 18001.

 

Renewed bizSAFE Level STAR in Work Safety and Health Council.

2016

 

Junction City Project Myanmar

Electrical services for office and commercial components for mixed development at Bogyoge Aung San Square at Yangon Myanmar

JEP

Erection of a Part 1 / Part 4 Storey Single User Industrial Development at Seletar Aerospace Crescent

 

ST Electronic (Omega 2)

Electrical Works to Proposed Erection of 6-Storey Industrial Development for ST Omega 2

 